NASA’s Wallops Island Beach Restoration Begins

Construction work to restore the beach and dunes protecting NASA’s Wallops Island Flight Facility damaged by super storm Sandy began on July 18.

Dredges from New Jersey-based Weeks Marine, Inc. are on-site, pumping sand from an off-shore borrow site and placing the sand along the beach restoring berm and dune elevations to levels that will protect NASA and Mid-Atlantic Spaceport infrastructure from strong, storm-generated wave damage from the Atlantic Ocean.

The more than $11 million project will place approximately 650,000 cubic yards of sand on the beach and is designed to reduce wave action before it reaches the rock seawall and sand dune system.

Hurricane Sandy pummeled the northern Virginia coast in late October of 2012, less than three months after the Norfolk District completed the original Wallops Island beach construction project.

According to George Mears, the Norfolk District project manager, “the beach performed as advertised” during the storm.

“Many at Wallops Flight Facility monitored the storm during the daylight hours using cameras mounted in several towers along the beach,” he said. “At the height of the storm, overwash wasn’t occurring anywhere along the new beach.”

Before the beach project, the launch range infrastructure was routinely subjected to overwash and sand accumulation during nor’easters or significant storms, Mears said.

Hurricane Sandy’s wave action caused little damage to Wallops Island’s infrastructure, which is nearly $1 billion in value; however, the hurricane took a toll on the new berms and dunes that was likely the equivalent of at least two to three years of projected erosion, Mears said.

Congress responded to NASA’s request for restoration funding with an emergency supplemental appropriation, which is paying for this restoration effort.

The restoration of the Wallops Island Shoreline is necessary to provide storm damage reduction for approximately $1.2 billion of Federal and State assets that support nearly $100 million annually in programs as well as the $1.9 billion International Space Station cargo resupply missions,” said Paul Bull, deputy division chief of facilities management at NASA’s Wallops Flight Facility.

A post-Sandy beach preliminary damage assessment conducted by Norfolk District revealed that the storm removed between 650,000 and 800,000 cubic yards of sand out of the total 3.2 million cubic yards placed on the beach during the original beach construction project.

Erosion that has occurred since the hurricane appears to be much closer to projections – roughly about 250,000 cubic yards per year from the beach and near shore, according to Norfolk District officials.

The emergency supplemental funding from Congress won’t restore the beach in August of 2014 to the way it was in August of 2012, but should come close to restoring most of the sediment lost during Hurricane Sandy. The goal is to effectively postpone the next replenishment to 2017 or 2018 as per the original beach design performance estimate.

The beach material is coming from a Bureau of Ocean Energy Management-managed borrow site about 14 miles from Wallops Island, by sea, and about 7 miles east of Assateague.

Press Release, July 25, 2014

Share this article

Follow Dredging Today

Events>

<< Feb 2017 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 1 2 3 4 5

National Coastal Restoration Conference – Christchurch

The first three days will include speakers, seminars and local field-trips around the Christchurch urban beaches and the local North Canterbury coast…

read more >

(ISP-IDFC) International Combined Conference on INTEGRATION OF SEA PORTS & INNOVATIONS IN DREDGING & FUTURE CHALLENGES

The combined conference will focus towards enhancing the ports capabilities by doing the integration of our major and minor ports across…

read more >

Africa Ports Expansion 2017

Join senior officials from Kenya Ports Authority, Egypt’s Port Said Port Authority, Tanzania Ports Authority, Ghana Ports and Harbours Authority, Mauritius Ports Authority, Nigeria Ports Authority and more to gain insights into their port development plans and identify opportunities for your business.

More Info http://bit.ly/2jHFlmM

read more >

Coast & Marine Structures 2017

Join the 9th Annual Coasts and Marine Structures 2017 conference

Discover Best Practise Strategies for Design, Planning, Construction and Asset Management

To remain competitive, Australian port operators must plan, design, manage and maintain their assets more creatively and proactively to meet future demands and drive profitability.

With this in mind, our Coast and Marine Structures Summit 2017 will focus on key considerations relevant to ensuring your existing assets are maximised and prepared to accommodate bigger vessels.

Hear from 20+ global experts including Maritime/Coastal Engineers, Contractors, Port Authorities and more, including GHD (USA), Indonesian Port Corporation (Asia), G-Group Consulting (New Zealand), Ausenco (Australia), Port Authority NSW (Australia), to name a few.

By attending this 2-day conference, you’ll learn about:

Innovative planning and design of ports to create efficiencies that drive profit
Best practice asset management strategies and new PIANC design principles for bulk terminals
Proactive asset management and maintenance to improve durability and maximise and extend asset lifecycles
Alternative material and protection techniques trialled and tested in the US and Europe
Strategies to shift organisational culture and mindset from asset management to asset maintenance
How you can leverage technology to increase the efficiency of your marine structures
Case studies on retrofitting, expanding and upgrading your ports in cost-effective ways
To learn more or book a ticket, contact us now!

W: http://www.marinestructures.com.au/ 

P: +61 2 9229 1000

E: enquire@iqpc.com.au

Read More

read more >

Jobs>

Network Support Engineer

As Network Support Engineer you will be responsible for the installation / configuration, operation and maintenance of the infrastructural....

apply

Dredge Masters, Engineers and Superintendent\\\\\\\'s Urgently Required!

Flagship Management is working with a number of leading international marine and dredging organizations and require the following candidates for a range of global projects...

apply

Design & Proposal Engineer Dredging

As Design & Proposal Engineer you translate customer requirements into the design of a vessel in close cooperation with...

apply