NASA’s Wallops Island Beach Restoration Begins

Beach Restoration Work for NASA’s Wallops Island Commences

Construction work to restore the beach and dunes protecting NASA’s Wallops Island Flight Facility damaged by super storm Sandy began on July 18.

Dredges from New Jersey-based Weeks Marine, Inc. are on-site, pumping sand from an off-shore borrow site and placing the sand along the beach restoring berm and dune elevations to levels that will protect NASA and Mid-Atlantic Spaceport infrastructure from strong, storm-generated wave damage from the Atlantic Ocean.

The more than $11 million project will place approximately 650,000 cubic yards of sand on the beach and is designed to reduce wave action before it reaches the rock seawall and sand dune system.

Hurricane Sandy pummeled the northern Virginia coast in late October of 2012, less than three months after the Norfolk District completed the original Wallops Island beach construction project.

According to George Mears, the Norfolk District project manager, “the beach performed as advertised” during the storm.

“Many at Wallops Flight Facility monitored the storm during the daylight hours using cameras mounted in several towers along the beach,” he said. “At the height of the storm, overwash wasn’t occurring anywhere along the new beach.”

Before the beach project, the launch range infrastructure was routinely subjected to overwash and sand accumulation during nor’easters or significant storms, Mears said.

Hurricane Sandy’s wave action caused little damage to Wallops Island’s infrastructure, which is nearly $1 billion in value; however, the hurricane took a toll on the new berms and dunes that was likely the equivalent of at least two to three years of projected erosion, Mears said.

Congress responded to NASA’s request for restoration funding with an emergency supplemental appropriation, which is paying for this restoration effort.

The restoration of the Wallops Island Shoreline is necessary to provide storm damage reduction for approximately $1.2 billion of Federal and State assets that support nearly $100 million annually in programs as well as the $1.9 billion International Space Station cargo resupply missions,” said Paul Bull, deputy division chief of facilities management at NASA’s Wallops Flight Facility.

A post-Sandy beach preliminary damage assessment conducted by Norfolk District revealed that the storm removed between 650,000 and 800,000 cubic yards of sand out of the total 3.2 million cubic yards placed on the beach during the original beach construction project.

Erosion that has occurred since the hurricane appears to be much closer to projections – roughly about 250,000 cubic yards per year from the beach and near shore, according to Norfolk District officials.

The emergency supplemental funding from Congress won’t restore the beach in August of 2014 to the way it was in August of 2012, but should come close to restoring most of the sediment lost during Hurricane Sandy. The goal is to effectively postpone the next replenishment to 2017 or 2018 as per the original beach design performance estimate.

The beach material is coming from a Bureau of Ocean Energy Management-managed borrow site about 14 miles from Wallops Island, by sea, and about 7 miles east of Assateague.

Press Release, July 25, 2014

Share this article

Follow Dredging Today

Events>

<< Jul 2015 >>
MTWTFSS
29 30 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

11th Annual Deepwater Intervention Forum

The 11th Annual Deepwater Intervention Forum is the platform for the Deepwater industry to learn about new subsea intervention technology…

read more >

2015 IEEE/OES Acoustics

The technical programme of RIO Acoustics 2015 encompasses the newest techniques and technologies to solve challenges in ocean engineering…

read more >

StormCon

Now entering its 14th year and serving a global audience StormCon is the premier event for stormwater pollution prevention and surface…

read more >

Coastal Engineering Asia

WHY YOU CANNOT MISS THIS EVENT

Join Trueventus Coastal Engineering Asia, a truly International platform presenting dynamic technical discussion on the present-day coastal engineering challenges. Topics namely on marine clay, dredge materials, flood mitigation and effective use of soil compression are of the many interesting topics presented.  Join us on this 2 days journey in defining coastal engineering well into the modern engineering history at the beautiful shores of Asia- Singapore!

KEY FEATURES OF THIS CONFERENCE

  • Hearing from the successful coastal projects
  • Gauging the key benefits of using soil compression method to strengthen soil
  • Mastering effective and cost-saving excavation and sediment disposal methods
  • Learning new innovations, techniques and technologies in marine structure engineering and construction
  • Exploring the advances in the field of design and construction of coastal structures

 More info

read more >

Jobs>

Senior Engineer

Gahagan & Bryant Associates, Inc. (GBA) is posting the following career opportunity in their Houston, TX and Baltimore, MD and Tampa, FL offices...

apply

Hydrographic Surveyor

Gahagan & Bryant Associates, Inc. (GBA) is posting the following career opportunity in their Houston, TX and Baltimore, MD and Tampa, FL offices....

apply