NASA’s Wallops Island Beach Restoration Begins

Beach Restoration Work for NASA’s Wallops Island Commences

Construction work to restore the beach and dunes protecting NASA’s Wallops Island Flight Facility damaged by super storm Sandy began on July 18.

Dredges from New Jersey-based Weeks Marine, Inc. are on-site, pumping sand from an off-shore borrow site and placing the sand along the beach restoring berm and dune elevations to levels that will protect NASA and Mid-Atlantic Spaceport infrastructure from strong, storm-generated wave damage from the Atlantic Ocean.

The more than $11 million project will place approximately 650,000 cubic yards of sand on the beach and is designed to reduce wave action before it reaches the rock seawall and sand dune system.

Hurricane Sandy pummeled the northern Virginia coast in late October of 2012, less than three months after the Norfolk District completed the original Wallops Island beach construction project.

According to George Mears, the Norfolk District project manager, “the beach performed as advertised” during the storm.

“Many at Wallops Flight Facility monitored the storm during the daylight hours using cameras mounted in several towers along the beach,” he said. “At the height of the storm, overwash wasn’t occurring anywhere along the new beach.”

Before the beach project, the launch range infrastructure was routinely subjected to overwash and sand accumulation during nor’easters or significant storms, Mears said.

Hurricane Sandy’s wave action caused little damage to Wallops Island’s infrastructure, which is nearly $1 billion in value; however, the hurricane took a toll on the new berms and dunes that was likely the equivalent of at least two to three years of projected erosion, Mears said.

Congress responded to NASA’s request for restoration funding with an emergency supplemental appropriation, which is paying for this restoration effort.

The restoration of the Wallops Island Shoreline is necessary to provide storm damage reduction for approximately $1.2 billion of Federal and State assets that support nearly $100 million annually in programs as well as the $1.9 billion International Space Station cargo resupply missions,” said Paul Bull, deputy division chief of facilities management at NASA’s Wallops Flight Facility.

A post-Sandy beach preliminary damage assessment conducted by Norfolk District revealed that the storm removed between 650,000 and 800,000 cubic yards of sand out of the total 3.2 million cubic yards placed on the beach during the original beach construction project.

Erosion that has occurred since the hurricane appears to be much closer to projections – roughly about 250,000 cubic yards per year from the beach and near shore, according to Norfolk District officials.

The emergency supplemental funding from Congress won’t restore the beach in August of 2014 to the way it was in August of 2012, but should come close to restoring most of the sediment lost during Hurricane Sandy. The goal is to effectively postpone the next replenishment to 2017 or 2018 as per the original beach design performance estimate.

The beach material is coming from a Bureau of Ocean Energy Management-managed borrow site about 14 miles from Wallops Island, by sea, and about 7 miles east of Assateague.

Press Release, July 25, 2014

Share this article

Follow Dredging Today

Events>

<< Mar 2015 >>
MTWTFSS
23 24 25 26 27 28 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Ocean Business 2015 Conference

More than just a static Exhibition Ocean Business already has an outstanding reputation for its training and demonstration programme, which…

read more >

Seminar on Dredging and Reclamation

This five-day course strives to provide an understanding through lectures by experts in the field and workshops, partly conducted on-site…

read more >

3rd MED Ports 2015

A two days Conference Programme will feature 30 world-class conference speakers addressing topical issues and challenges on global…

read more >

Underwater Sound in Relation to Dredging

It was compiled by the WODA Expert Group on Underwater Sound, under the remit of the WODA Environmental Commission, and reviewed by experts…

read more >

Jobs>

Multiple Positions available for dredging project in Malaysia

Hall Contracting has recently been awarded a contract in Johor Bahru, Malaysia. They are currently looking for a Cutter Suction Dredge 1st and 2nd Operator...

apply

Proposal Designer Special Projects

You work together with our salesteam, finding creative solutions to meet customers demands but build effieciently as usual and produce effectively ass well. Je create broad ship designs and adapt it for specific customer demands. Besides, you prepare specifications...

apply

Controller international projects

Project controllers are part of the project team abroad, responsible for setting up, implementing, and managing Finance and Control issues on-site at projects and in our offices all over the world...

apply