Final approval from the U.S. Army Corps of Engineers was received on Friday, meaning that the Tahoe Keys Marina dredging program will probably begin next week.

The Tahoe Keys Marina dredging project will involve removal of accumulated sand in the east channel to the approved depth of 6,215 feet, announced Tahoe Daily Tribune.

A total of 4,200 cubic yards of material will be removed from the mentioned area with an excavator stationed on a floating barge and turbidity curtains will be used during the dredging process to help contain suspended sediment.

The marina officials said they expect this dredging scheme to be wrapped up by June 1.