CCCC 4th Harbour Co. Bags Bid for Jinhai Phase 2 Land Forming Project (China)

On November 17, CCCC Fourth Harbour Engineering Co., Ltd. (CCCC 4th Harbour Co.) won the bid for the foundation treatment works of Jinhai Phase 2 in Lianyungang Coastal New Area.

The project is an integral part of Jinhai Phase 2 land forming project and the infrastructure of Lianyungang Coastal New Area. With a foundation treatment area of 127,578 square kilometers and a planned construction period of 306 days, the project will consolidate the foundation with the technology of deep vacuum preloading, the method of deep vacuum-surcharge preloading, and the method of vacuum-surcharge preloading plus shallow replacement.

The project will promote the implementation of Lianyungang’s strategic plan of “moving east, embracing sea”, and is of great importance to Lianyungang’s economic and social development.

[mappress]

Dredging Today Staff, December 2, 2011;