USA: Manatee Pocket Dredging Completed

Manatee Pocket Dredging Completed

After 18 months and the removal of approximately 280,000 cubic yards of sediment, the channel dredging of the Manatee Pocket is now complete.

The resulting 100-foot wide main channel has already greatly improved navigation and access to the pocket and its tributaries, providing economic benefits as well as enhancements to the natural environment and water quality.

Mechanical dredging work will continue for an additional two months as additional sediments are removed from the Pocket as part of the private dredging portion of this project. The dredging contractor has also begun the process of removing sediment from the material handling site located on US-1 and demobilizing dredging equipment throughout the pocket.

The entire demobilization process is expected to be complete within the next few months. The $13 million dredging project, coordinated by Martin County, was funded primarily through grants from the local, state and national programs.

About the Manatee Pocket Project

The Manatee Pocket Project is a dredging project that entailed the removal of approximately 280,000 cubic yards of sediment from the Manatee Pocket in Port Salerno.

Dredging of the Manatee Pocket began in July 2010. Now that it is essentially complete, the project has resulted in a 100-foot-wide channel that provides navigational and environmental enhancements to the Manatee Pocket and its adjacent waterways as well as important economic benefits for the surrounding communities.

The $13 million dredging project, coordinated by Martin County, was funded primarily through grants from the local, state and national programs.

[mappress]

Dredging Today Staff, January 23, 2012; Image: manateepocketproject