Malaysia: Rajang River Dredging Progresses Well

According to Borneo Post, the Rajang River dredging project at near Pulau Kerto is expected to be completed by the end of June. This project began at the end of January, and to date, 55 per cent of the project had been done, five per cent ahead of schedule. “The riverbed invert levels would be [&hel

1 minutes read

According to Borneo Post, the Rajang River dredging project at near Pulau Kerto is expected to be completed by the end of June.

This project began at the end of January, and to date, 55 per cent of the project had been done, five per cent ahead of schedule.

“The riverbed invert levels would be dredged to RL – 5m, and the volume of materials to be dredged is 610 cubic meters. The dredged materials consist mainly of sand and mud,” stated Simon Lau , the company’s executive director.

The project is undertaken by Hock Seng Lee Berhad.

[mappress]

Dredging Today Staff, April 2, 2012;

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.