DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›News›USA: Dredging Plan for Lower and Middle James River Introduced
News

November 17, 2012 · about 13 years ago

USA: Dredging Plan for Lower and Middle James River Introduced

Under the authority of FAR 6.302-1, the U.S. Army Corps of Engineers intends to negotiate on a sole source basis a contract to Orion Dredging Services, LLC. This sole source contract is required for maintenance dredging portions of the Lower and Middle James River Federal Navigation Project with com

2 minutes read
  • LinkedIn
  • X
  • Email

Under the authority of FAR 6.302-1, the U.S. Army Corps of Engineers intends to negotiate on a sole source basis a contract to Orion Dredging Services, LLC.

This sole source contract is required for maintenance dredging portions of the Lower and Middle James River Federal Navigation Project with completion of period of performance on 14 February 2013.

The existing single award task order contract (SATOC) used to perform maintenance dredging on the James River was awarded to Orion Dredging Company using full and unrestricted competition on 28 June 2010 for a maximum amount of $9,000,000.00. The SATOC consisted of a base year with two optional years. The base year and both optional years have been awarded and are represented by three task orders (TO), one task order per year, respectively.

Contract capacity was reached during execution of TO number 3 due to an unexpected amount of additional shoaling that resulted from recent storm events and exacerbated by Hurricane Sandy. This effort is a contained in the scope of TO#0003, but the base IDIQ ceiling has been reached.

The dredging contract will include the removal of approximately 500,000 cubic yards of dredge material from the James River Federal Navigation Project with overboard placement of the material occurring adjacent to the project’s dredging locations.

Dredging will be required to an elevation of -26 feet Mean Lower Low Water, with one foot of additional dredging depth allowed. The estimated dollar value for the proposed action is $2,000,000 which reflects the total cost to dredge in the following channels. The work will be performed in Tribell Shoal Channel, Dancing Point-Swan Point Channel, and Jordan Point-Harrison Bar-Windmill Point Shoal Channel.

[mappress]

Press Release, November 18, 2012

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

News

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EXCLUSIVE: GRSE, Damen sign MoU on construction of advanced dredgers
  2. 2Lyttelton Port gears up for its largest expansion project
  3. 3Isle of Palms wraps up first phase of beach renourishment
  4. 4Conneaut Harbor dredging kicks off

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free