DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›News›USA: King County Creek Restoration About to Begin
News

May 7, 2013 · about 13 years ago

USA: King County Creek Restoration About to Begin

The U.S. Army Corps of Engineers will begin the first phase of construction in May on the Big Spring Creek Restoration Project on the Enumclaw Plateau in southeast King County. This project will relocate a major section of Big Spring Creek from the current ditched system into a channel consistent wi

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers will begin the first phase of construction in May on the Big Spring Creek Restoration Project on the Enumclaw Plateau in southeast King County.

This project will relocate a major section of Big Spring Creek from the current ditched system into a channel consistent with its historic route. This restoration effort will reduce pollution coming from roadside ditches, restore native vegetation, and improve fish and wildlife habitat, including coho salmon and cutthroat trout. Currently, very little native vegetation or instream habitat features are associated with the stream.

For more than 100 years, the Green/Duwamish River watershed was altered in a way that degraded its ability to provide clean, productive habitat for fish and wildlife. The Green/Duwamish River Ecosystem Restoration Project is a comprehensive restoration program for the entire watershed, spanning the tidal estuaries to the spawning and wildlife habitat areas in the upper basin. Big Spring Creek is part of this watershed. This stream was diverted in the 1930s into roadside ditches to make nearby land more suitable for farming. Currently, Big Spring Creek is severely channelized, and a portion of its flow pattern traverses roadside ditches, which receive road runoff, degrading water quality of the stream.

Construction of Phase 1 of the project (the southern portion) will require heavy equipment operation during the summer of 2013 for up to three months. Phase 2 of the project (the northern portion) is planned for the summer of 2014. Construction activity is scheduled between 7:30 a.m. and 5:30 p.m. All work will take place within existing conservation easements or on public land.

The project is sponsored by The Army Corps of Engineers and King County Department of Natural Resources and Parks. The Corps is responsible for project implementation. Support for this project comes from other entities including the City of Enumclaw, the King Conservation District, and Water Resources Inventory Area 9.

[mappress]

Press Release, May 7, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

News

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: TSHD Gateway completes Chiapas dredging job
  2. 2Tender process underway for Point Vernon dredging
  3. 3Advancing the Lower Passaic River Superfund cleanup
  4. 4EIB provides EUR100M for Klaipėda Port development

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free