Qatar: Plan for Doha New Port Moves in Right Direction

Plan for Doha New Port Moves in Right Direction

On July 3, the number of prefabricated blocks of Qatar Doha New Port Project reached 20,000, accounting for 57.84% of the total number of prefabricated blocks, and 3773 blocks more than the output of the project reference plan for the same period.

This provides powerful guarantee for the block installation and the follow-up construction of wharf structure.

Qatar Doha New Port Project is a dug-into port; the wharf adopts the of solid concrete block gravity structure; the total number of prefabricated blocks is 34578; and the amount of prefabricated concrete is 1,060,000m3.

[mappress]

Press Release, July 25, 2013