DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Corps Schedules Repair of Point Chehalis Revetment (USA)
Business & Finance

November 7, 2013 · about 13 years ago

Corps Schedules Repair of Point Chehalis Revetment (USA)

The U.S. Army Corps of Engineers, Seattle District, has scheduled to begin work Nov. 11 to repair and restore a 300-foot reach of the Point Chehalis revetment, including a 60-foot reach that could fail during a severe storm. The Corps has awarded a contract to Rognlin’s Inc. of Aberdeen, Wash., for

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Seattle District, has scheduled to begin work Nov. 11 to repair and restore a 300-foot reach of the Point Chehalis revetment, including a 60-foot reach that could fail during a severe storm.

The Corps has awarded a contract to Rognlin’s Inc. of Aberdeen, Wash., for $500,600 to complete the work by approximately Dec. 11.

The Point Chehalis Revetment is a system of 3,100 feet of armor stone revetment and six groins. The system is designed to provide protection of the coast line from strong and dynamic coastal wave action. Since 2000, there has been increased wave energy at the revetment and is related to significant change in bathymetry – depth measurements – through the harbor mouth.

Wave overtopping frequency continues to increase damage to both the revetment and groins. Several sections of the western end of the revetment are failing due to loss of armor stone as a result of annual severe winter storms.

An emergency repair was undertaken to fix an approximately 100-foot weak spot in advance of a moderately large coastal storm event Oct. 23-24, 2010.

The revetment is 2-3 feet below authorized height in areas where the structures core material dislodged from the structure. Displaced core material has led to overall loss of structure stability.

Construction activities have been coordinated with the City of Westport and Port of Grays Harbor.

The section of revetment under repair will be closed to the public during construction. “No Public Access” signs will be posted at the entrance.

The section of revetment being repaired will be quite dangerous. Between the on-site heavy equipment, 6-17 ton rocks that are not yet placed and can shift, and truck traffic, the boardwalk and beach on either side of the repair area will be periodically closed. No one will be allowed within the construction zone on the revetment.

[mappress]

Press Release, November 8, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Boskalis and Van Oord begin IJsselmeerdijk project
  2. 2USACE completes West Harbor dredging project
  3. 3EXCLUSIVE: GRSE, Damen sign MoU on construction of advanced dredgers
  4. 4Lyttelton Port gears up for its largest expansion project

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free