DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Atlantic Support Bags Point Judith Harbor Jetty Contract (USA)
Business & Finance

December 26, 2013 · about 12 years ago

Atlantic Support Bags Point Judith Harbor Jetty Contract (USA)

The Point Judith Harbor east jetty in Narragansett, Rhode Island, will be repaired under the terms of a $627,000.00 contract issued recently by the U.S. Army Corps of Engineers, New England District. Work will be accomplished by Atlantic Support Installations, Inc., of Hopedale, Mass. Construction i

1 minutes read
  • LinkedIn
  • X
  • Email

The Point Judith Harbor east jetty in Narragansett, Rhode Island, will be repaired under the terms of a $627,000.00 contract issued recently by the U.S. Army Corps of Engineers, New England District.

Work will be accomplished by Atlantic Support Installations, Inc., of Hopedale, Mass. Construction is scheduled to start on or about Feb. 15, 2014 and take about three months to complete. The contract was awarded on Dec. 19, 2013.

The work for this project consists of repairing the East Jetty at the Point Judith Harbor of Refuge in Narragansett. Repairs involve the mobilization and demobilization, and the furnishing, delivery and placement of new stone to replace stones displaced during Hurricane Sandy in October 2012 and to fill in existing gaps and low points along the jetty.

“The repairs will be performed to restore the southerly portion of the East Jetty to the original profiles and cross-sections, ” said Project Manager Michael Walsh, of the Corps’ New England District, Programs/Project Management Division in Concord, Mass. “ Repairs will require substantial moving and manipulation of existing stones to obtain the required interlocking placement.”

Mobilization of equipment and rehabilitation of the jetty may require a combination of land and marine construction methods and resources. The project will be managed by the Corps and all work will be accomplished under the supervision of a Corps’ Quality Assurance Representative to assure compliance with contract requirements.

[mappress]

Press Release, December 27, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  2. 2Stockton closes boat launch due to dredging work
  3. 3E-touch Dredgers: Work on new TSHD progresses steadily
  4. 4USACE begins Lower Charleston Harbor maintenance dredging

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free