DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›GUPC Announcement of Suspension Goes Against Third Set of Locks Contract
Business & Finance

January 19, 2014 · about 12 years ago

GUPC Announcement of Suspension Goes Against Third Set of Locks Contract

The Panama Canal Authority (ACP) has warned that the suspension announced for today by Grupo Unidos por el Canal, S.A. (GUPC) is not valid, lacks merit and goes against what is established in the Contract for the Design and Construction of the Third Set of Locks. Currently, the production levels are

2 minutes read
  • LinkedIn
  • X
  • Email

The Panama Canal Authority (ACP) has warned that the suspension announced for today by Grupo Unidos por el Canal, S.A. (GUPC) is not valid, lacks merit and goes against what is established in the Contract for the Design and Construction of the Third Set of Locks.

Currently, the production levels are low in the new locks project without any justification.

The suspension announced on December 30, 2013 and reiterated by GUPC Thursday, January 16, 2014 in a letter to the ACP, is based on the wrongful application of Sub-Clause 16.1 of the Contract – cited by the consortium to justify the suspension – because this clause provides the right to suspend work only when the employer has failed to issue payment to the contractor. However, this is not the case and, therefore, such notice of intent to suspend work lacks merit. In fact, the ACP pays GUPC within the first 15 days after the invoice is presented, significantly in advance of the contractually-stated period of 56 days.

Furthermore, during the weekend, ACP has maintained communication with the head of Sacyr, leader of the consortium GUPC, to find a solution to the current situation. The ACP will review all proposals presented formally and always within the provisions of the contract.

In addition, the ACP rigorously and continuously monitors the developments in the field in order to keep track of everything that involves a reduction of work and the suspension announced for tomorrow. Today, the ACP Administrator, executives and technical personnel conducted an inspection of the construction site in the Pacific to witness first-hand the progress.

[mappress]

Press Release, January 20, 2014

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free