DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Corps to Present Indiana Harbor 2014 Dredging Schedule (USA)
Business & Finance

March 5, 2014 · about 12 years ago

Corps to Present Indiana Harbor 2014 Dredging Schedule (USA)

The U.S. Army Corps of Engineers and Indiana Harbor and Canal (IHC) dredging contractors, Kokosing Construction Co. and O’Brien & Gere, will hold a public meeting March 13, 2014, to present the IHC 2014 dredging schedule and activities. This meeting will take place at East Chicago City Hall, 4525 In

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers and Indiana Harbor and Canal (IHC) dredging contractors, Kokosing Construction Co. and O’Brien & Gere, will hold a public meeting March 13, 2014, to present the IHC 2014 dredging schedule and activities.

This meeting will take place at East Chicago City Hall, 4525 Indianapolis Blvd. (2nd floor), East Chicago, Ind. 46312.

Dredging began in 2012 at IHC confined disposal facility (CDF) for the first time since 1972, with the contractor dredging approximately 400,000 cubic yards of material. Dredging will resume in the spring of 2014.

Portions of the federal channel will be dredged to achieve the congressionally-authorized navigation depths. Sediments in adjacent berthing and docking areas will be removed at the request of local industry and local sponsor, the East Chicago Waterway Management District.

After backlog dredging is complete, maintenance dredging will take place, as necessary, over a period of approximately 20 years, to remove re-accumulated sediments and maintain navigable depths in the waterway.

[mappress]

Press Release, March 6, 2014

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Boskalis and Van Oord begin IJsselmeerdijk project
  2. 2USACE completes West Harbor dredging project
  3. 3EXCLUSIVE: GRSE, Damen sign MoU on construction of advanced dredgers
  4. 4Lyttelton Port gears up for its largest expansion project

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free