DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Australia: Burnett River Dredging Wrapped Up
Business & Finance

May 26, 2014 · about 12 years ago

Australia: Burnett River Dredging Wrapped Up

Neumann Contractors have recently completed dredging works in Queensland’s Burnett River near Kirby’s Wall. The job involved deepening the navigational channel and placement of the material behind “Kirby’s Wall”. Neumann performed the work using their 450mm cutter suction dredger Nu Endeavour couple

1 minutes read
  • LinkedIn
  • X
  • Email

Neumann Contractors have recently completed dredging works in Queensland’s Burnett River near Kirby’s Wall. The job involved deepening the navigational channel and placement of the material behind “Kirby’s Wall”.

Neumann performed the work using their 450mm cutter suction dredger Nu Endeavour coupled to a spreader barge for placement.

The work was required following recent severe flooding, with joint funding provided by the Qld Department of Transport and Main Roads and the Department of Natural Resources and Mines.

The Burnett River was severely impacted by flooding in January 2013. Dredging was required to restore the depth of the river’s navigational channels adjacent to Kirby’s Wall. A total of 65,700 cubic metres of sand and gravel was removed from the channels and placed behind Kirby’s Wall.

Two specific dredge areas were nominated by TMR:

– Dredge Area A, adjacent and upstream of Kirby’s Wall required 36,000m3 of material to be removed;

– Dredge Area B, downstream of Kirby’s Wall with almost 30,000m3.

Both dredge areas were required to be dredge to a maximum depth of 2.3m below LAT. The dredged material was required to be placed behind Kirby’s Wall to fill in the area between the river bank and the rock wall.

[mappress]

Press Release, May 27, 2014

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Boskalis and Van Oord begin IJsselmeerdijk project
  2. 2USACE completes West Harbor dredging project
  3. 3EXCLUSIVE: GRSE, Damen sign MoU on construction of advanced dredgers
  4. 4Lyttelton Port gears up for its largest expansion project

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free