DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Rivers Parrett and Tone Dredging Project on Track (UK)
Business & Finance

September 28, 2014 · about 12 years ago

Rivers Parrett and Tone Dredging Project on Track (UK)

A 20 year flood action plan for a long-term sustainable future for the Somerset Levels and Moors is in full swing with a 8km dredge of the Tone and Parrett Rivers well underway. The plan is owned by Somerset’s councils, internal drainage boards and local leaders and was prepared in partnership with

1 minutes read
  • LinkedIn
  • X
  • Email

A 20 year flood action plan for a long-term sustainable future for the Somerset Levels and Moors is in full swing with a 8km dredge of the Tone and Parrett Rivers well underway.

The plan is owned by Somerset’s councils, internal drainage boards and local leaders and was prepared in partnership with local and national organizations including the Environment Agency.

At the moment, seven crews are dredging Rivers Parrett and Tone.

On the River Parrett the work continues to dredge the Westonzoyland Pumping Station, Ham Lawn Farm and at the confluence of the Rivers Parrett and Tone with the usage of the floating machinery.

On the River Tone the amphibious excavator and a land based excavator are working between Currymoor Pumping Station and Athelney Railway Bridge and there are two land based excavators working upstream of the railway bridge.

So far, approximately 107,000m³ of silt has been removed from the two rivers. Still the contractors have 1.9km of river (3.8km of total river bank length) left to dredge and remain on programme to complete work by the end of October.

Over the next couple of weeks the focus of the contractors will be:

[mappress]

September 29, 2014

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  2. 2Stockton closes boat launch due to dredging work
  3. 3E-touch Dredgers: Work on new TSHD progresses steadily
  4. 4USACE begins Lower Charleston Harbor maintenance dredging

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free