Tolers Cove Marina Dredging Underway

Marcol Dredging Company started the Tolers Cove Marina dredging project on February 16, with their dredger ‘Captain Joe’.

According to the U.S. Coast Guard, dredge spoils will be deposited via pipeline across the Intracoastal Waterway at the Upland Confined Disposal Facility.

Dredging will continue 24 hours per day, 7 days per week basis until approximately 31 March, 2015.

Mariners are urged to use caution while transiting the area.