McLaughlin & Harvey Completes Invergordon Project

McLaughlin & Harvey has just announced the completion of Invergordon Service Base project in Cromarty Firth.

The project, named redevelopment of the Invergordon Service Base Phase 3, included design and construction of the site that will be used as a modern functioning service base.

During the works, McLaughlin & Harvey completed reclamation of approx 380,000sqft of land using dredged material from the simultaneous Nigg South Quay Development, 500m of rock armor revetment and 160m of combi-pile anchor wall to form a new deep water quay.

The company was awarded this £19.1 million contract for the redevelopment of the Invergordon Service Base back in May 2014.