DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Navarre Beach Dune Restoration About to Begin
Business & Finance

March 21, 2016 · about 10 years ago

Navarre Beach Dune Restoration About to Begin

The Navarre Beach Dune Restoration project could begin as early as late April and will include placing of approximately 1.6 million cubic yards of sand east of the Gulf Islands National Seashore to the eastern limits of the beach Marine Park. According to the Santa Rosa County, the project construct

1 minutes read
  • LinkedIn
  • X
  • Email

The Navarre Beach Dune Restoration project could begin as early as late April and will include placing of approximately 1.6 million cubic yards of sand east of the Gulf Islands National Seashore to the eastern limits of the beach Marine Park.

According to the Santa Rosa County, the project construction will make use of the same offshore borrow area used for the initial 2006 restoration project.

Works will restore the dune crest to a width of 30 feet with native dune plants and increase the width of the beach berm by 100 to 200 feet.

On December 10, 2015, the Santa Rosa County Board of County Commissioners awarded a construction contract to Weeks Marine Inc.

The contractor’s most recent “ Order of Work & Project Schedul e” cites Weeks Marine’s intent (subject to possible changes) to:

For the project, Weeks Marine will use two trailing suction hopper dredges – the “R.N. Weeks” and the “B.E. Lindholm” – to excavate sand from the offshore borrow area.

Following completion of sand placement in Navarre Beach, the contractor has also indicated his intent to use the same two dredges to construct the Pensacola Beach project.

[mappress mapid=”22134″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EXCLUSIVE: Van Oord's dredger Utrecht returns to Itajaí
  2. 2Weeks Marine completes beach nourishment in Nags Head
  3. 3BREAKING NEWS: Pinglu Canal passes completion acceptance inspection
  4. 4Split hopper dredger Trud R busy at the Seaway

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free