Causeway Bay Typhoon Shelter Scheme in Full Swing

The Causeway Bay Typhoon Shelter project is progressing towards its next phase, which involves the marine works inside the area.

With immediate effect and for a period of approximately 15 months, marine works involving dredging operations, temporary reclamation, construction of temporary seawall and construction of tunnel will be carried out within the area, according to the Hong Kong Marine Department (MARDEP).

These operations will be carried out by a flotilla of vessels, including one grab dredger, four hopper barges, seven derrick barges, some tugs and work boats.

The number of vessels engaged in the works will change from time to time to suit operational requirements.

A working area of approximately 50 meters around the dredger will be established, together with the silt curtain extending from the sea surface to the seabed.

Share this article

Follow Dredging Today

Events>

<< Oct 2019 >>
MTWTFSS
30 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31 1 2 3

CEDA Dredging Days 2019

The conference is well-attended by professionals representing the entire cross-section of the dredging field…

read more >

2019 Western Dredging Association Gulf Coast Chapter Annual Meeting

The meeting will provide a forum for the exchange of information of interest to the dredging industry and its associates.

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply