Restart of the Oceanside Harbor Dredging Project

Progress on the navigational dredging project within Oceanside Harbor continued last week with the contractor, CJW Construction, returning to the site to restart the operations.

The contractor restarted the dredging on July 6th, and in just two days managed to remove some 5,000 cubic yards of material from the harbor’s entrance channels.

To date, CJW has dredged about 30,000 cubic yards of the 260,000 cubic yards designated for removal.

Material dredged from the entrance channels is being placed along Oceanside’s beach, beginning immediately south of the San Luis Rey River mouth to a point about 150 yards south of the pier.

Placement of material is currently occurring in front of the North Coast Village and will move south towards Surfrider Way in the next week.

Share this article

Follow Dredging Today

Events>

<< Jan 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

Navingo Career Event 2020

The Navingo Career Event is Europe’s biggest career event for the maritime,…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply