DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Small Setback for Oceanside Harbor Dredging Project
Business & Finance

September 25, 2016 · about 10 years ago

Small Setback for Oceanside Harbor Dredging Project

Maintenance dredging within Oceanside Harbor continued last week with the contractor, CJW Construction, reporting having removed approximately 34,220 cubic yards of material from the harbor’s entrance channels from September 15 through 21. According to the U.S. Army Corps of Engineers, Los Angeles D

1 minutes read
  • LinkedIn
  • X
  • Email

Maintenance dredging within Oceanside Harbor continued last week with the contractor, CJW Construction, reporting having removed approximately 34,220 cubic yards of material from the harbor’s entrance channels from September 15 through 21.

According to the U.S. Army Corps of Engineers, Los Angeles District, the contractor reported one day lost to large ocean swells in this reporting period.

Forecasted sea conditions are anticipated to preclude further dredging until October 4.

Since the start of operations, June 6th 2016, CJW has dredged approximately 209,990 cubic yards out of the 260,000 designated for removal.

The Oceanside Harbor navigational dredging project, one of four annual dredging projects conducted by the Corps Los Angeles District, is conducted to maintain the federal channels within Oceanside Harbor at their authorized federal depth and to provide safe navigation for the recreational, commercial and military vessels that use the channels.

Material dredged from the entrance channels is being placed along Oceanside’s beach. Placement of beach quality material along the shoreline is a beneficial byproduct of the maintenance dredging project. CJW is currently discharging material just north of the Oceanside pier.

[mappress mapid=”23045″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Boskalis and Van Oord begin IJsselmeerdijk project
  2. 2USACE completes West Harbor dredging project
  3. 3EXCLUSIVE: GRSE, Damen sign MoU on construction of advanced dredgers
  4. 4Lyttelton Port gears up for its largest expansion project

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free