Business & Finance

about 10 years ago

Hilton Head Island Beach Nourishment Project Advances

Work to repair hurricane damage to the previously constructed beach along the south central oceanfront (North and South Forest Beach) is complete, reports the Town of Hilton Head Island. The Town’s contractor, Weeks Marine Inc., has rebuilt the beach to the point where they were prior to Hurricane M

1 minutes read

Work to repair hurricane damage to the previously constructed beach along the south central oceanfront (North and South Forest Beach) is complete, reports the Town of Hilton Head Island.

The Town’s contractor, Weeks Marine Inc., has rebuilt the beach to the point where they were prior to Hurricane Matthew near Shipyard/Palmetto Dunes.

“ As a result of the impact of the storm, Town hereby announces a change in the limits to two (2) of the four (4) of the acceptance segments along the central oceanfront portion of the work ,” said HHI in the release.

Currently, the active work area is near Wendover Dunes in southern Palmetto Dunes.

Now, work is will advance approximately 3,500 feet to near Captain’s Walk before the dredge is repositioned and beach fill operations begin near Singleton Beach. This represents a shift in the breakpoint only.

According to the Town, the completion of this revised section is expected within the next 10 days.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.