DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Hastings Coastal Defense Scheme Underway
Business & Finance

November 14, 2016 · about 9 years ago

Hastings Coastal Defense Scheme Underway

Tonnes of granite arrived in Hastings on Tuesday, November 8th as the phase 1 of the town’s coastal defense improvement plan starts. Two new rock groynes will be created with 45,000 tonnes of granite, which will be delivered in stages from Norway by barge. Once the new rock groynes have been complet

1 minutes read
  • LinkedIn
  • X
  • Email

Tonnes of granite arrived in Hastings on Tuesday, November 8th as the phase 1 of the town’s coastal defense improvement plan starts.

Two new rock groynes will be created with 45,000 tonnes of granite, which will be delivered in stages from Norway by barge.

Once the new rock groynes have been completed, 25,000 tonnes of shingle from the beach will be moved back from Hastings’ harbor arm to protect the sea wall.

The £4 million scheme is expected to take around 10 weeks to complete, depending on the weather.

Andrew Martin, Mackley Project Manager , said: “ Delivery of the rock boulders can only take place at high tide while conversely, construction of the rock groynes and moving shingle on the beach can only take place at low tide.

As such we will be working at any time of the day or night, including Sundays, according to the state of the tide, in order to maintain momentum and progress works as quickly as possible.”

The project is almost entirely funded by a Flood Defense Grant in Aid, from Department for Environment, Food, and Rural Affairs (DEFRA), with Hastings Council contributing £30,000 towards the scheme.

[mappress mapid=”23246″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free