DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USACE to Complete Menemsha Creek Dredging Project
Business & Finance

July 26, 2017 · about 9 years ago

USACE to Complete Menemsha Creek Dredging Project

A new contractor has been selected to dredge the remaining sandy shoal material in the Menemsha Creek Federal navigation project (FNP) in Aquinnah and Chilmark, Martha’s Vineyard, Mass. The U.S. Army Corps of Engineers, New England District, terminated the prior dredging company in March 2017 after

2 minutes read
  • LinkedIn
  • X
  • Email

A new contractor has been selected to dredge the remaining sandy shoal material in the Menemsha Creek Federal navigation project (FNP) in Aquinnah and Chilmark, Martha’s Vineyard, Mass.

The U.S. Army Corps of Engineers, New England District, terminated the prior dredging company in March 2017 after it did not complete all work last season.

On June 7, 2017, the Corps signed a take-over agreement with the project’s bonding company, U.S. Specialty Insurance Company, of Houston, Texas, to hire a new firm to complete the remaining dredging, and repair those items which were damaged by the previous contractor.

The selected dredging firm, H & L Dredging, of Bay Shores, New York, will begin mobilization of equipment in mid-September 2017 and dredging is scheduled to start on or about October 1, 2017 and take about 4-5 weeks to complete, reported the Corps.

“ The remaining effort to complete the project consists of hydraulically dredging up to approximately 39,000 cubic yards of sandy material in the Federal channel connecting Vineyard Sound to Menemsha Pond ,” said Project Manager Craig Martin, of the Corps’ New England District, Programs/Project Management Division in Concord, Mass.

The sandy dredge material will be pumped via pipeline about 1.5 miles west along Lobsterville Beach to the placement site near an area of erosion adjacent to State Road in Aquinnah.

Dredging and disposal will be performed between October 1st and January 15th to minimize impact to natural resources in the area.

[mappress mapid=”24307″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EXCLUSIVE: Van Oord's dredger Utrecht returns to Itajaí
  2. 2Weeks Marine completes beach nourishment in Nags Head
  3. 3BREAKING NEWS: Pinglu Canal passes completion acceptance inspection
  4. 4Split hopper dredger Trud R busy at the Seaway

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free