Kaliningrad Sea Canal Dredging Resumes
Maintenance dredging operations resumed on the Kaliningrad Sea Canal at the end of July 2017, according to the FSUE “Rosmorport” North-Western Basin Branch.
The suspension of maintenance dredging operations for more than three months has been conditioned due to fish spawning in the region and the need to assemble flexible adapters that help connect coastal disposal site and operating dredgers, reported the branch.
In order to organize the delivery of additional 350.000 cubic meters of sediment to coastal disposal sites, the Kaliningrad Directorate of the North-Western Basin Branch used the break to carry out needed repairs on PK Picket 130.
Preparatory and associated works have been also carried out to take sediments on the coastal disposal on PK Picket 130, added the Rosmorport.
During the repairs, banking-up of the coastal disposal on PK 214 has been complete and at least 530 meters of new pipes have been laid.
List of related news articles
-
Posted: 8 days ago
Rosmorport successfully completes 2020 dredging season
FSUE “Rosmorport” has announced the successful completion of the 2020 maintenance dredging season. I...
Posted: 8 days ago -
Posted: 15 days ago
Contract signed for the new Pionersky terminal
Inter RAO-Engineering and FSUE Rosmorport have signed contract for the construction of the new Pione...
Posted: 15 days ago -
Posted: about 1 month ago
Hopper barge Morskaya handed over to Rosmorport
FSUE Rosmorport has taken delivery of the self-propelled hopper barge Morskaya, the Russian company ...
Posted: about 1 month ago -
Posted: 26 days ago
Inter RAO to build new terminal in Pionersky
Inter RAO – Engineering LLC (member of Inter RAO Group) has been announced as the winner of FS...
Posted: 26 days ago