DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Donjon Marine Makes Good Progress in Old Saybrook
Business & Finance

February 25, 2018 · about 8 years ago

Donjon Marine Makes Good Progress in Old Saybrook

The state of Connecticut together with the contractor, Donjon Marine of Hillside (NJ), is continuing maintenance dredging of the North Cove Federal Navigation Project in Old Saybrook. The project has been maintained a number of times since it was authorized, with the most recent past dredging event

2 minutes read
  • LinkedIn
  • X
  • Email

The state of Connecticut together with the contractor, Donjon Marine of Hillside (NJ), is continuing maintenance dredging of the North Cove Federal Navigation Project in Old Saybrook.

The project has been maintained a number of times since it was authorized, with the most recent past dredging event in 2008.

At that time, 175,000 cubic yards of sediment were removed, but due to funding constraints the authorized dimensions of the project were not obtained.

The current cycle of maintenance was initiated by the town of Old Saybrook when availability of the project began to be impacted during times of low tide.

Dredging areas include the 11-foot deep entrance channel, 11-foot deep anchorage and 6-foot deep anchorage. Donjon Marine is performing the work under a $4.3 million contract awarded Sept. 20, 2017.

The contractor started dredging on Nov. 14, 2017, and has removed about 230,000 cubic yards of material from the project so far. Approximately 286,000 cubic yards of predominantly silty sediment will be removed by mechanical dredge.

Around 56,000 cubic yards of material still needs to be dredged from the 6-foot anchorage area by the coordinated dredging window ending on March 31.

This project is unique for the District employing a second trans-loading dredge to transfer shoal material from small hopper scows used to access shallow portions of the project to large capacity dump scows. After the trans-loading process is complete the large dump scows are hauled to the Central Long Island Sound Disposal Site, about 35 miles away from the project, and placed at predesignated coordinates.

Additionally, the project will deploy a turbidity curtain during the latter stages of the project to allow dredging to continue into time of year restrictions to protect sensitive species. Despite equipment breakdowns and cold weather resulting in several inches of ice within the project, the contractor expects to complete the project this dredging season.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free