DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Littlehampton Flood Defenses Complete
Business & Finance

June 18, 2018 · about 8 years ago

Littlehampton Flood Defenses Complete

Team Van Oord has completed a project to fill a 28-meter gap in the flood defenses in the West Sussex town of Littlehampton – in turn reducing the flood risk for 2,000 homes. Working on behalf of the Environment Agency, the 20-week project included organizing the planning application and producing t

2 minutes read
  • LinkedIn
  • X
  • Email

Team Van Oord has completed a project to fill a 28-meter gap in the flood defenses in the West Sussex town of Littlehampton – in turn reducing the flood risk for 2,000 homes.

Working on behalf of the Environment Agency, the 20-week project included organizing the planning application and producing the detailed design, followed by installation of a sheet piled wall and concrete capping beam alongside the River Adur.

The installation of the sheet piles took place from a jack-up barge, supporting a 70t crawler crane. The barge arrived in a good weather window, having been transported from Tilbury. The barge was then towed into the harbor and loaded with equipment – before being towed along the river, floated through a pedestrian bridge and moved into position at the work site.

The 18m piles were selected to complement the existing adjacent piles and to provide a 50-year life span. Pile stability was enhanced by increasing the section size, rather than length – which would have meant driving into a band of hard material, with the risk of vibration damage to an adjacent 130 year old cob stone building.

“Our combination of construction and design expertise enabled us to produce a design which overcame complex ground conditions – including buried timber and a perched water table – while maintaining flood defense levels at all times,” Barry Holt, Team Van Oord Project Manager said. “ Throughout the project, we worked with the harbor master and local businesses to ensure the river road remained open at all times to minimize disruption for local residents.”

The project was completed with a backfill between the new and old defenses of self-compacting granular fill. This filled the main voids and stabilized the ground immediately behind the new wall. The last gap in the wall was closed by installing new flood glass.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EXCLUSIVE: GRSE, Damen sign MoU on construction of advanced dredgers
  2. 2Lyttelton Port gears up for its largest expansion project
  3. 3Isle of Palms wraps up first phase of beach renourishment
  4. 4Conneaut Harbor dredging kicks off

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free