Gowanus Canal Dredging Program Progresses

The U.S. Environmental Protection Agency (EPA) said in its latest announcement that this week marks the one-year anniversary of their Superfund Task Force Report.

Image source: EPA's Gowanus Canal Group

The Superfund Task Force was commissioned to provide recommendations on how EPA could streamline and improve the Superfund program.

EPA has made significant progress in carrying out the report’s recommendations. The Agency also finalized its plans for completing all 42 recommendations by the end of 2019, which are outlined in a new 2018 Update to the Superfund Task Force recommendations,” they stated.

EPA has improved the health, living conditions, and economic opportunity of thousands of people living near Superfund sites over the past year as the Agency worked to implement the Task Force recommendations,” said EPA Acting Administrator Andrew Wheeler.

I am proud of the accomplishments achieved by EPA’s hardworking staff, and we will continue to engage directly with stakeholders and communities near Superfund sites to accelerate cleanup and promote economic revitalization. Our plan to complete Task Force recommendations by the end of 2019 will ensure this work continues as one of EPA’s highest priorities.”

Yesterday, EPA Regional Administrator Pete Lopez, Dan Wiley, Congresswoman Nydia M. Velázquez’s District Director for Southwest Brooklyn, other dignitaries and community members looked on as the dredging and capping pilot project at the Gowanus Canal Superfund site in Brooklyn, N.Y. enters its final phase.

Under EPA oversight, approximately 17,000 cubic yards of contaminated sediment have been dredged from the Gowanus Canal’s 4th Street turning basin. Work is currently underway to cap the bottom. said EPA.

Under the pilot project, steel sheet piles walls were installed along the sides of the canal to allow dredging work to be performed safely and sediment was removed and taken off-site for treatment and disposal. In the final phase, layers of sand, clay, and activated carbon-absorbing materials will be placed on the turning basin bottom to create a clean canal bottom.

The pilot study began in October 2017 and is expected to be completed later this fall.