DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›The Myrtle Beach Works in Full Swing
Business & Finance

October 8, 2018 · about 8 years ago

The Myrtle Beach Works in Full Swing

Pretty soon, the more than 15 million visitors each year to both Folly Beach and the Grand Strand will have new sand to set their chairs on. Stabilizing beaches and dunes through renourishment is a critical mission of the U.S. Army Corps of Engineers. The Charleston District is concurrently renouris

2 minutes read
  • LinkedIn
  • X
  • Email

Pretty soon, the more than 15 million visitors each year to both Folly Beach and the Grand Strand will have new sand to set their chairs on.

Stabilizing beaches and dunes through renourishment is a critical mission of the U.S. Army Corps of Engineers.

The Charleston District is concurrently renourishing both Folly Beach and the Grand Strand, consisting of Myrtle, North Myrtle, and Garden City/Surfside beaches, in order to minimize the impacts to people and infrastructure during a storm event like South Carolina has seen in each of the previous three years.

The $10 million Folly Beach project is being funded through federal emergency beach rehabilitation funding from Hurricanes Matthew and Irma. Through the project, approximately 750,000 cubic yards of material are being placed on Folly Beach.

“ The project is unique in that it is considered a beneficial use project ,” said Wes Wilson, project manager. “ The material being placed on the beach is being dredged from Folly River, clearing the federal channel for recreational and commercial boaters, meaning two projects are being completed at once.”

This $34.8 million Myrtle Beach project is 100 percent federally funded and will place approximately 1.4 million cubic yards of material across the three reaches that make up the project. This follows up the 1.3 million cubic yards of sand that were placed just last year in North Myrtle and Garden City/Surfside beaches through emergency funding due to Hurricanes Matthew and Joaquin.

The Myrtle Beach project is scheduled to be completed in December. Work on each project happens 24 hours a day, seven days a week, and approximately 500 feet of beach is completed per day.

As a portion of the projects are taking place during sea turtle nesting season, the contractor is complying with the requirements of the Endangered Species Act and the Marine Mammals Protection Act.

By Sean McBride, USACE Charleston District

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free