Damen DOP200 for Amsterdam Job

On the North-Eastern outskirts of Amsterdam a vital lock complex controls the water levels and salinity of the inland waters.

Recently, Paans Van Oord renovated the lock complex, which was a major challenge in the short time frame available.

The full job lasted only 4 weeks, and the crammed program included a wide range of renovation and repair jobs to the lock sill and lock head. In order to clean the lock bottom, the company used the DOP submersible dredge pump with a special suction head.

The DOP200 was mounted on the boom of a Liebherr R954C EW excavator, which had been placed on crane barge “Anna-Catharina”.

According to the company, only 3 days were required by the DOP200 and crew to clean the lock bottom – which has a surface of just over 1.000m². The sediment was pumped in a barge located alongside the crane barge, Damen said.

 

Share this article

Follow Dredging Today

Events>

<< Mar 2020 >>
MTWTFSS
24 25 26 27 28 29 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Navingo Career Event 2020

The Navingo Career Event is Europe’s biggest career event for the maritime,…

read more >

Jobs>

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply