DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Ponce de Leon Inlet Dredging Schedule Updated
Business & Finance

December 20, 2018 · about 7 years ago

Ponce de Leon Inlet Dredging Schedule Updated

The U.S. Army Corps of Engineers announced yesterday schedule changes to maintenance dredging of Ponce de Leon Inlet and pumping sediment to the near-shore of New Smyrna Beach in Volusia County. The near-shore work naturally nourishes the beach via wave action, which then helps reduce risk to landsi

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers announced yesterday schedule changes to maintenance dredging of Ponce de Leon Inlet and pumping sediment to the near-shore of New Smyrna Beach in Volusia County.

The near-shore work naturally nourishes the beach via wave action, which then helps reduce risk to landside infrastructure.

The Corps’ contractor, Cavache, Inc. of Pompano Beach Florida, will not conduct operations Dec. 24-26, and Dec. 31 – Jan. 1. The team will work a day shift only, about 10-12 hours daily, Dec. 27-30, reported the Corps.

Starting Jan. 2, Cavache will return to 24-hour operations daily until project completion.

According to the Project Manager Beau Corbett, inclement weather has delayed operations since the project started in August. Working 24 hours daily is required to complete the project on schedule.

“ The operational changes support the local community as well as the contractor during the holiday period. We’ll transition back to 24-hour operations after the holidays to get the work completed by April 30 ,” Corbett said.

If the weather cooperates, the Corps anticipates the booster pump currently located “in the river” in the vicinity of Beachway Avenue, New Smyrna Beach, will be relocated to the south of the island in the vicinity of Crawford Road. It will remain at this location until the end of the project, operating 24-7.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free