DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›GLDD Getting Ready for the Post Florence Renourishment Project
Business & Finance

February 26, 2019 · about 7 years ago

GLDD Getting Ready for the Post Florence Renourishment Project

Great Lakes Dredge & Dock Company (GLDD) has begun mobilizing land- and water-based pipe, heavy equipment and personnel for the upcoming Post Florence Renourishment Project. The Carteret County reported yesterday that the first batch of land-based piping has arrived at the Indian Beach 4WD Ramp and

1 minutes read
  • LinkedIn
  • X
  • Email

Great Lakes Dredge & Dock Company (GLDD) has begun mobilizing land- and water-based pipe, heavy equipment and personnel for the upcoming Post Florence Renourishment Project.

The Carteret County reported yesterday that the first batch of land-based piping has arrived at the Indian Beach 4WD Ramp and is actively being staged along the beachfront.

According to the County, both the Indian Beach 4WD Ramp and Dog Leg 4WD Drive Access will be used to transfer land-based dredge pipe and other heavy equipment needed for the project.

The Post Florence project will utilize 945,446 cubic yards of sand obtained from the Offshore Dredged Material Disposal Site (ODMDS) associated with Morehead City Federal Navigation Project.

Under the plans, GLDD’s dredge Liberty Island will begin dredging/nourishment operations in the first week of March, followed by the Ellis Island that will arrive on the site several weeks later.

The project is scheduled to be completed by April 30, 2019.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1The largest annual dredging work on Great Lakes in full swing
  2. 2Pacific Dredge completes Port of San Diego dredging
  3. 3Ellicott delivers another Mud Cat to Canada
  4. 4Dredging work underway near Lancelin jetty

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free