Metedeconk River Dredging Underway

The next round of dredging operations in the Metedeconk River is now underway, according to the Brick Township officials. The project, which began late last year, is part of a $16 million scheme to continue returning channels in Barnegat Bay to a state of good repair. The first few days will consist

1 minutes read

The next round of dredging operations in the Metedeconk River is now underway, according to the Brick Township officials.

The project, which began late last year, is part of a $16 million scheme to continue returning channels in Barnegat Bay to a state of good repair.

The first few days will consist of work during the daytime, and will eventually ramp up to a 24/7 project, the officials said.

They also added that the early start will allow the contractor to start dredging in the Green Cove Channel which has limited access due to tide and lack of overall space.

Upon completion of the Green Cove Channel, the contractor will move to the Mantoloking 4 Channel, which is near the Bayside Swamp Cove Park and along the waterfront homes (off Normandy Drive).

Below is the anticipated schedule:

Officials anticipate that the contractor for the project, H&L Contracting, will complete the works this fall due to the presence of spawning winter flounder in the winter and early spring.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.