DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Kissimmee River Restoration Works Underway
Business & Finance

June 23, 2019 · about 7 years ago

Kissimmee River Restoration Works Underway

The U.S. Army Corps of Engineers’ Jacksonville District is notifying Kissimmee River boaters of navigational restrictions along approximately ten miles of the river in the lower river basin. According to the notice, USACE continues backfilling the channelized Kissimmee River segments to allow flows

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers’ Jacksonville District is notifying Kissimmee River boaters of navigational restrictions along approximately ten miles of the river in the lower river basin.

According to the notice, USACE continues backfilling the channelized Kissimmee River segments to allow flows through the historic river channel and restore its floodplain and habitat.

Restoration construction will limit navigation, restricting it from U.S. Highway 98 to approximately 7 miles upstream and 3 miles downstream of U.S. Highway 98, reported the Corps.

“ We hope the public will continue enjoying the river and canals, and also continue to exercise extra caution in the waterways, particularly when approaching segments that are and will be closed for construction purposes ,” said Dr. Orlando Ramos-Gines, senior project manager .

The Corps anticipates completing construction activities in the summer of 2020.

The Kissimmee River restoration project is one of the many ongoing projects currently underway by the Army Corps of Engineers, in partnership with the South Florida Water Management District, to restore America’s Everglades.

Once completed, the Kissimmee River Restoration project will restore the 22-mile channelized river back to its natural meandering pattern and provide 130,000 acre-feet of natural floodplain storage.

This will slow the flow of water from the Kissimmee Basin into Lake Okeechobee, thereby slowing down the rise in the lake that often results in high-volume discharges to the Caloosahatchee and St. Lucie estuaries.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Boskalis and Van Oord begin IJsselmeerdijk project
  2. 2USACE completes West Harbor dredging project
  3. 3EXCLUSIVE: GRSE, Damen sign MoU on construction of advanced dredgers
  4. 4Lyttelton Port gears up for its largest expansion project

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free