DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›North Portsea Planning Application Gets OK
Business & Finance

July 31, 2019 · about 7 years ago

North Portsea Planning Application Gets OK

The next phase of plans to protect North Portsea Island from the risk of coastal flooding are underway following approval of the planning application for the first package of work in the Kendall’s Wharf area of North Portsea Island. The principal design for Phase 4 of the North Portsea Island Coasta

1 minutes read
  • LinkedIn
  • X
  • Email

The next phase of plans to protect North Portsea Island from the risk of coastal flooding are underway following approval of the planning application for the first package of work in the Kendall’s Wharf area of North Portsea Island.

The principal design for Phase 4 of the North Portsea Island Coastal Defense Scheme is now complete and will be delivered in two packages of work.

The first, 4a, will begin in September 2019 now that planning approval has been granted and includes the construction of an earth embankment, a steel sheet pile wall and raising the road adjacent to Kendall’s Wharf on Eastern Road.

This work is expected to be completed by April 2020.

The planning application for the second work package, 4b, along Eastern Road is due to be submitted in August 2019. The work includes the construction of a seawall along 2.4km of the Eastern Road, encasing the existing seawall and raising the defense level by approximately 1.2m.

Subject to planning approval, work should begin on these defenses in April 2020 with a view to being completed in late 2022.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free