DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USACE Completes Breach Closure on Levee L550 Near Watson
Business & Finance

August 25, 2019 · about 7 years ago

USACE Completes Breach Closure on Levee L550 Near Watson

The U.S. Army Corps of Engineers, Omaha District completed a breach closure on levee L550 near Watson, Missouri Saturday. This initial closure of breach L-550-A-I near river mile 542.8 stops the inflows of water, thereby allowing for the start of follow-on construction activities aimed at increasing

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Omaha District completed a breach closure on levee L550 near Watson, Missouri Saturday.

This initial closure of breach L-550-A-I near river mile 542.8 stops the inflows of water, thereby allowing for the start of follow-on construction activities aimed at increasing the level of flood risk management to approximately the 4% Annual Chance Exceedance (25-yr) level for this section of the L-550 Levee System until the system can be fully rehabilitated, reported the Corps.

The original contract of $22.1 million was awarded to Weston Solutions, Inc. of West Chester, PA June 11, 2019, and construction began July 8.

“ The USACE team has partnered very well with Weston Solutions and their key subcontractor, Hendrickson, to place 250,000 cubic yards of alluvial sand in the initial breach closure ”, said Dustin Davis, USACE Resident Engineer .

There are more than 500 miles of levees on the Missouri, Platte and Elkhorn rivers, and tributaries that have experienced significant flood damage since March 2019.

Due to the magnitude of damage along these levees, repair of the levee system efforts will take an extended period of time to execute.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Boskalis and Van Oord begin IJsselmeerdijk project
  2. 2USACE completes West Harbor dredging project
  3. 3EXCLUSIVE: GRSE, Damen sign MoU on construction of advanced dredgers
  4. 4Lyttelton Port gears up for its largest expansion project

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free