DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Hayling Island Works Wrap Up
Business & Finance

November 10, 2019 · about 6 years ago

Hayling Island Works Wrap Up

Eastern Solent Coastal Partnership (ESCP) said in their latest announcement that the beach nourishment works on Hayling Island are now successfully completed. The 2nd November storm event, which occurred the day after the dredger left site, overtopped the beach, leaving shingle and seawater on the p

1 minutes read
  • LinkedIn
  • X
  • Email

Eastern Solent Coastal Partnership (ESCP) said in their latest announcement that the beach nourishment works on Hayling Island are now successfully completed.

The 2nd November storm event, which occurred the day after the dredger left site, overtopped the beach, leaving shingle and seawater on the promenade (typical of a storm event of such magnitude).

“We worked closely with our contractors Royal Boskalis Westminster and Les Searle Group, taking advantage of their availability and expertise to deliver a rapid response to reform the beach levels and clear the promenade of shingle with minimal disruption, ready for winter,” said ESCP.

The works lasted 3 weeks in total and involved the movement of approximately 40,000m³ of shingle, deposited via a pump-ashore from the dredger, the Sospan Dau, and from beach recycling.

The first two weeks work on site involved the dredging of shingle material from the Chichester Harbor Approach Channel 24/7; deepening the channel to allow safe navigation in to Chichester Harbor (with the ESCP working in partnership with Chichester Harbor Conservancy), and providing shingle nourishment for the beach at Eastoke.

For the second week, trucks were mobilized to site to move the shingle to key locations, and profile the beach to design.

The Sospan Dau left site on 1st November having completed the expected works, said ESCP.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free