DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Massive Gladstone Dredging Project Step Closer to Reality
Business & Finance

December 9, 2019 · about 6 years ago

Massive Gladstone Dredging Project Step Closer to Reality

Gladstone Ports Corporation Limited (GPC) recently finalized the Environmental Impact Statement (EIS) for the proposed $760 million Gatcombe and Golding Cutting Channel Duplication Project. The project seeks to duplicate the existing shipping channels, beneficial reuse of dredged material in land re

2 minutes read
  • LinkedIn
  • X
  • Email

Gladstone Ports Corporation Limited (GPC) recently finalized the Environmental Impact Statement (EIS) for the proposed $760 million Gatcombe and Golding Cutting Channel Duplication Project.

The project seeks to duplicate the existing shipping channels, beneficial reuse of dredged material in land reclamation, and upgrade associated infrastructure in the Port of Gladstone, Queensland.

It will improve the existing and future safe passage of vessels within the port as throughput and associated vessel numbers increase.

The major dredging component of the project involves deepening and widening of the existing Gatcombe and Golding Cutting bypass shipping channels, resulting in two shipping channels of the same depth to allow an improved two-way passage into the port under all weather and tidal conditions.

The proposed duplicate channel will be approximately 15km long and dredging is proposed to be undertaken to an ultimate depth of -16.1m LAT, with a channel width (toe to toe) of 200m.

This equates to the removal of approximately 12.6 million cubic meters of seabed material (including dredging tolerance) from the Gatcombe and Golding.

In addition to the 12.6Mm³ of dredging for the Gatcombe and Golding Cutting Channels, initial dredging of approximately 250,000m³ of seabed material is proposed to establish a 2.3km long access channel to allow barges to transport dredged material from the shipping channels to the BUF.

The total estimated project dredging volume is 12.85 million cubic meters of seabed material.

If all goes according to schedule, this massive dredging project could begin as early as 2023.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Willapa Harbor dredging underway
  2. 2Dredging begins on Gugu River in Pampanga
  3. 3Boskalis Nederland: Work on Fish Migration River Afsluitdijk in full swing
  4. 4New sand arrives at West Beach and Henley Beach South