Government Awards JAXPORT Additional $93M for Channel Deepening

The federal government has allocated $93 million for the next phase of deepening the Jacksonville shipping channel to 47 feet from its current depth of 40 feet.

Image source: JAXPORT

A milestone for the project and a major victory for JAXPORT, the federal government has now fully funded the government’s portion of deepening through JAXPORT’s Blount Island Marine Terminal.

Of the total $93 million investment, $57,543,000 is included in the U.S. Army Corps of Engineers’ Fiscal Year 20 Work Plan, and an additional $35,457,000 is allocated in the A Budget for America’s Future – President’s Budget FY 2021.

“This is the first time JAXPORT has ever received funding in the President’s budget, which speaks volumes about the significance of this project to the Southeast U.S. and the nation,” said JAXPORT CEO Eric Green. “We are extremely grateful to our federal, state and local partners, as well as the dedication and leadership of the JAXPORT Board, for their steadfast support of our growth and the 138,000 jobs Jacksonville’s seaport generates in Florida.”

Upon completion of the deepening project, the SSA Jacksonville Container Terminal at Blount Island will feature a vessel turning basin and have the ability to simultaneously accommodate two post-Panamax vessels.

Harbor deepening is divided into four segments, contracts A-D, which make up the full length of the 13-mile federally authorized project.

The current funding model covers the project’s first 11 miles through Blount Island (contracts A, B and C). Contractors for the U.S. Army Corps of Engineers are scheduled to complete the first 5.5 miles in spring 2020, marking the halfway point for this portion of the project.

Harbor deepening began in February 2018 and is anticipated to be complete in 2023, two years ahead of its original schedule, based on continued funding from all partners.