Surveying Felidhoo Harbor

A survey operations for breakwater, revetment and quay wall for the V. Felidhoo Harbor extension project were successfully completed on March 28,2020, the Maldives Transport and Contracting Company (MTCC) reports. The work focused on detailed surveys including bathymetry of basin and channel, bathym

1 minutes read
Surveying Felidhoo Harbor
Image source: MTCC

A survey operations for breakwater, revetment and quay wall for the V. Felidhoo Harbor extension project were successfully completed on March 28,2020, the Maldives Transport and Contracting Company (MTCC) reports.

The work focused on detailed surveys including bathymetry of basin and channel, bathymetry of potential harbor expansion area, elevation profile from harbor area to the vegetation line and scaled aerial photography of entire island and harbor area.

According to MTCC, the survey will help to develop a detailed design for the harbor extension project.

MTCC signed the contract for this project on September 5, 2019.

Director General of Planning Ministry, Fathimath Shana Farooq, inked the agreement on behalf of the Maldives Government and MTCC CEO, Hassan Shah, put his signature on behalf of the company.

The project is estimated to cost $1.2 million and is expected to be completed in 210 days.

Advertisement

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.