DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Tema Port Expansion Completed Ahead of Schedule
Business & Finance

May 11, 2020 · about 6 years ago

Tema Port Expansion Completed Ahead of Schedule

Meridian Port Services Limited (MPS) successfully completed the entire Phase 1 works of the Tema Port Expansion Project in Ghana (also known as Terminal 3 of Tema Port) on April 30, 2020. “As per the terms of the Concession, MPS Terminal 3 was expected to Go-Live on 28th June 2019 on 2 berths and th

1 minutes read
  • LinkedIn
  • X
  • Email
Tema Port Expansion Completed Ahead of Schedule
Image source: APM

Meridian Port Services Limited (MPS) successfully completed the entire Phase 1 works of the Tema Port Expansion Project in Ghana (also known as Terminal 3 of Tema Port) on April 30, 2020.

“As per the terms of the Concession, MPS Terminal 3 was expected to Go-Live on 28th June 2019 on 2 berths and the entire Phase 1 works were due to be completed on 28th June 2020. Both due dates were successfully achieved and works were completed ahead of schedule,” said APM Terminals in their latest release.

Under the project, the new harbor basin was created on a 3km long beach directly on the Atlantic Ocean and right on the Meridian Timeline.

Building into the sea, from the beach, the breakwater root goes 1,550m into the ocean with a 2km long arm extending eastwards from the root of the breakwater parallel to the quay wall. The 3,558m long breakwater is harboring a vast 450 hectares (1,110 Acres) of maritime waterfront, said APM.

The new harbor basin is accessible through a 3,500m long by 225m wide Entrance Channel into a turning basin/circle of 500m diameter.

The Access Channel has been dredged to -18.7m, Turning Basin to -17.4m and -16.9m by the quay wall to accommodate 16m draft vessels to dock alongside all berths.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Dredging Africa presents new CSD
  2. 2Premier Marinas submits Brighton dredging application
  3. 3Dredging underway at Everett Harbor and Snohomish River
  4. 4PD Ports opens new Marine facility

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free