The Napier Port 6 Wharf project is coming along nicely and is set to complete on time, by the end of 2022.
According to the latest update, the contractor – HEB Construction – has so far made good progress with piling, having installed 13 piles out of 400 that will support the wharf.
With progress on track for the first section of the wharf, preparatory work for piling the second 200 metre section has started.
This prep work involves:
Once all that is complete, piling in this second section can start.
Napier Port also announced that Heron Construction Co has started dredging in the berth pocket, disposing material at the offshore disposal area.
So far, the team have dredged around 30,000 cubic metres of the total 1.3 million cubic metres that will be dredged during the project.
