Fohdhoo coastal works move forward

Work on coastal protection structures at N. Fohdhoo is well underway, with 58% project progress so far, Maldives Transport and Contracting Company (MTCC) said in their latest release. “We are currently working on back-fill area leveling works and geo bag filling which will be used for revetment cons

1 minutes read
Fohdhoo coastal works move forward
Image source: MTCC

Work on coastal protection structures at N. Fohdhoo is well underway, with 58% project progress so far, Maldives Transport and Contracting Company (MTCC) said in their latest release.

“We are currently working on back-fill area leveling works and geo bag filling which will be used for revetment construction,” MTCC said.

The project involves sand filtering works of 1,400cbm; sand filling for geo bags; and sand back-filling works of 5,000cbm; placing of geo bags along 180m area.

According to MTCC, the project will help protect the area from coastal erosion.

The estimated value of the scheme is around $500,000.

The project – awarded on 25th February 2020 and received EIA Approval on 18th March 2020 – is estimated to be completed in 180 days.

Advertisement

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.