DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Dredgit wraps up Fawn Lake dredging
Infrastructure

October 19, 2020 · about 5 years ago

Dredgit wraps up Fawn Lake dredging

The Town of Bedford, MA, yesterday released the latest update about their Fawn Lake Dredging Program. As of October 16th, the Dredgit crew has completed the dredging operation at Fawn Lake. Also, they have removed the dewatering equipment. The materials storage bin has been dismantled and the lawn a

1 minutes read
  • LinkedIn
  • X
  • Email
Dredgit wraps up Fawn Lake dredging
Dredgit

The Town of Bedford, MA, yesterday released the latest update about their Fawn Lake Dredging Program.

As of October 16th, the Dredgit crew has completed the dredging operation at Fawn Lake. Also, they have removed the dewatering equipment.

The materials storage bin has been dismantled and the lawn area will be regraded, said the Town.

A total of 8,076 cy of bottom sediment and 350 cy of floating/submerged aquatic vegetation were removed from the site.

In addition to complying with all the environmental conditions, Dredgit has reported 3,060 accident-free man-hours on the project.

During a regular inspection, the DPW Grounds Manager found two hitching posts which were submerged in the east side of the lake.

According to Don Corey from the Bedford Historical Society, the 200-pound cast iron posts were circa 1880. The posts will be stored at DPW until the Society has a proper place to display them.

Dredgit has started to draw down the water level in preparation for work at the dam.

Once the level is maintained, Dredgit’s subcontractor will be back to install the aqua-dam to contain the water and allow work to be done in the dry.

Any muck along the outlet will be removed and structural gravel will be placed as the face of the dam. Dam work will continue through the end of November, as such, the trails in that area remain closed, said the Town.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Infrastructure

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free