DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Damaged Mill Creek levees repaired
Operations & Maintenance

March 9, 2021 · about 5 years ago

Damaged Mill Creek levees repaired

Sections of the Mill Creek Levee System that were damaged during the February 2020 flooding are now repaired thanks to the efforts of the Army Corps’ Walla Walla District and their contractor TDX Power Services. This was a partnership project with the levee sponsor, the Mill Creek Flood Control Zone

1 minutes read
  • LinkedIn
  • X
  • Email
Damaged Mill Creek levees repaired
USACE

Sections of the Mill Creek Levee System that were damaged during the February 2020 flooding are now repaired thanks to the efforts of the Army Corps’ Walla Walla District and their contractor TDX Power Services.

This was a partnership project with the levee sponsor, the Mill Creek Flood Control Zone District, operated by Walla Walla County.

Mill Creek had a record flood event in early February 2020, causing extensive erosion damage throughout both banks of the levee system.

These levees were built using gabions (wire-bound cells filled with cobbles) as armor protecting the riverside slopes of the levees.

During the flood, some of the gabions, along with portions of the riprap revetments, were damaged and had to be reconstructed.

On Dec. 1, 2020, the Corps awarded a contract to TDX Power Services to rehabilitate more than eighty damage sites along the federal portion of the Mill Creek Levees. The total value of the contract was just over $2 million dollars.

The repairs will provide increased protection for over $3 billion of property in the area around the Mill Creek Levee System.

The Corps’ Mill Creek General Investigation Feasibility Study is ongoing and will be completed this year. The recommended plan includes additional levee improvements in six locations between the Mill Creek Diversion Dam and Gose Street.

Other elements of the recommended plan include three repairs in the concrete channel and a change to project operations.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Operations & Maintenance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free