DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business development›Round Valley Reservoir rehabilitation moves ahead
Business development

April 26, 2021 · about 5 years ago

Round Valley Reservoir rehabilitation moves ahead

Major excavation works at the North Dam – the dam that faces Lebanon Borough – officially started earlier this week, the New Jersey Water Supply Authority (NJWSA) reports. According to their latest project update, soils will be excavated from the downstream (north facing) slope of the embankment and

1 minutes read
  • LinkedIn
  • X
  • Email
Round Valley Reservoir rehabilitation moves ahead
roundvalleyproject.com

Major excavation works at the North Dam – the dam that faces Lebanon Borough – officially started earlier this week, the New Jersey Water Supply Authority (NJWSA) reports.

According to their latest project update, soils will be excavated from the downstream (north facing) slope of the embankment and stockpiled. Excavation will proceed from the crest (top) to the toe of the embankment.

“Stone and sand will be placed in the excavation to filter and collect any water that may seep through the embankment from the reservoir. The excavated soils and topsoil will be re-placed over the new sand and stone filter and the structure will look largely the same after construction,” said NJWSA.

The North Dam project area has four sediment control basins with diversion channels and outlet structures complete with skimmers, and overflow spillways.

Sediment control basins help to control soil erosion during construction. Each basin has been placed to capture runoff and control erosion and sediment from the embankment excavation itself or from a staging and stockpiling area.

Work at the North Dam will be ongoing through at least late 2021.

Concurrently, excavation and other embankment rehabilitation work at the Dike is ongoing and is expected to continue for at least several more months.

Work at the South Dam is expected to start later this year following completion of the Dike and the South Dam construction will continue throughout 2022.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business development

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free