Fountain Lake dredging project progresses nicely

A survey conducted two days ago by the dredging contractor, J.F. Brennan Company, Inc. shows the dredging progress in the Main Bay and Dane’s Bay to date. As reported, over 337,000 cubic yards have been removed from Fountain Lake during Phase 2. In total, the contractor J.F. Brennan will remove appr

1 minutes read
Fountain Lake dredging project progresses nicely
Shell Rock River Watershed District (SRRWD)

A survey conducted two days ago by the dredging contractor, J.F. Brennan Company, Inc. shows the dredging progress in the Main Bay and Dane’s Bay to date.

As reported, over 337,000 cubic yards have been removed from Fountain Lake during Phase 2.

In total, the contractor J.F. Brennan will remove approx. 380,000 cubic yards of sediment this year. This work is expected to be wrapped up by mid-August.

The first phase included removal of over 700,000 cubic yards of sediment out of the Edgewater Bay.

After the second phase of dredging, the third and final phase will complete the Fountain Lake Restoration Project.

The third phase includes Main Bay (East Basin), Bancroft Channel and parts of Bancroft Bay.

Advertisement

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.