DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Ganga dredging nears completion
Infrastructure

May 24, 2021 · about 5 years ago

Ganga dredging nears completion

The ongoing dredging work in the Ganga on a stretch between Ramnagar Fort and Malviya rail-road bridge is nearing completion, The Times of India reports. The piles of sand removed from the Ganga has helped create a sand island that could be used to host various activities. “We had started this proje

1 minutes read
  • LinkedIn
  • X
  • Email
Ganga dredging nears completion
Ganga Jadhav facebook

The ongoing dredging work in the Ganga on a stretch between Ramnagar Fort and Malviya rail-road bridge is nearing completion, The Times of India reports.

The piles of sand removed from the Ganga has helped create a sand island that could be used to host various activities.

“We had started this project worth Rs 11.95 crores ($1,6 million) in March. Maximum work of creating a new channel of Ganga stream on the right bank has been completed and the project will be over by June 15. The work done so far has turned the sandbanks between the two channels in an island shape,” said irrigation department’s executive engineer Pankaj Verma.

“This multipurpose project is reducing the velocity of water flow which was eroding ghat steps and threat to historical buildings was increasing. While creating a new channel we have ensured the actual stream does not shift away from the ghats,” he added.

“The work has been done in such a way that when the project is fully complete, 60% river water will pass through the old stream on the left bank and the remaining 40% will be through the new channel towards the right bank.”

The average depth of river on the ghat side is 10 metres, while the depth of the new channel is 7-8 metres.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Infrastructure

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EXCLUSIVE: Van Oord's dredger Utrecht returns to Itajaí
  2. 2Weeks Marine completes beach nourishment in Nags Head
  3. 3BREAKING NEWS: Pinglu Canal passes completion acceptance inspection
  4. 4Split hopper dredger Trud R busy at the Seaway

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free