DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Townsville’s $232 million channel project moving on
Infrastructure

August 15, 2021 · about 5 years ago

Townsville’s $232 million channel project moving on

After reaching a major milestone with the completion of the 2.2km rock wall, the Port of Townsville’s $232 million Channel Upgrade project is moving to the next phase. This includes construction of an unloading facility which will be used to offload dredge material into the reclamation area. The 150

1 minutes read
  • LinkedIn
  • X
  • Email
Townsville’s $232 million channel project moving on
Port of Townsville

After reaching a major milestone with the completion of the 2.2km rock wall, the Port of Townsville’s $232 million Channel Upgrade project is moving to the next phase.

This includes construction of an unloading facility which will be used to offload dredge material into the reclamation area.

The 150m unloading facility is being built on the western boundary of the rock wall, with the work expected to take up to four months.

According to the port officials, all piling work associated with the construction will be conducted during daylight hours, Monday to Saturday, to ensure impacts are minimised for nearby residents and businesses. Marine observers will be in place to immediately stop work if any dolphins, dugong, whales or turtles venture too close.

They also added that dredging to widen Townsville’s 14.9-kilometre shipping channel will begin very soon, with all dredge material to be placed in a 62-hectare reclamation area bounded by the rock wall.

As reported earlier, the dredging is expected to take two years, with the project set for completion in late 2023.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Infrastructure

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free