DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business development›McAmis wraps up first full season of MCR work
Business development

October 20, 2021 · about 4 years ago

McAmis wraps up first full season of MCR work

J.E. McAmis has just released the latest update on their work at the Mouth of the Columbia River (MCR) South Jetty project. The Chico based heavy civil marine contractor, along with major subcontractor Rognlins Construction, and the USACE Portland District worked very hard all year to complete repai

1 minutes read
  • LinkedIn
  • X
  • Email
McAmis wraps up first full season of MCR work
Michael Mathers

J.E. McAmis has just released the latest update on their work at the Mouth of the Columbia River (MCR) South Jetty project.

The Chico based heavy civil marine contractor, along with major subcontractor Rognlins Construction, and the USACE Portland District worked very hard all year to complete repairs to the Mouth of the Columbia River (MCR) South Jetty from Station 153+75 out to 221+50.

To date, more than 240,000 tons of jetty stone ranging in size from 4 tons to 40 tons has been delivered to the MCR South Jetty site.

According to J.E. McAmis Vice President and Senior Project Manager, Scott Vandegrift , “J.E. McAmis will continue to quarry our own stone this winter in several permitted locations throughout the Pacific Northwest and will be prepared to barge an additional 120,000 tons of jetty stone to site in 2022 and again in 2023.”

It is anticipated that the completion of the estimated 480,000-ton project will occur in Q3 2023.

The team has run out of consistent safe working weather this year and will resume placement operations in May 2022.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business development

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free