DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Eustis’ Third Port completes dredging project
Infrastructure

August 8, 2022 · about 4 years ago

Eustis’ Third Port completes dredging project

Joint Base Langley-Eustis’ Third Port, the U.S. Army’s pier complex sitting where Skiffe’s Creek meets the James River, completed a multi-month dredging project recently. The dredging, a 24/7 operation taking place April 18 – June 15, was part of a regularly scheduled maintenance, which occurs every

2 minutes read
  • LinkedIn
  • X
  • Email
Eustis’ Third Port completes dredging project
Patrick Bloodgood, USACE

Joint Base Langley-Eustis’ Third Port, the U.S. Army’s pier complex sitting where Skiffe’s Creek meets the James River, completed a multi-month dredging project recently.

The dredging, a 24/7 operation taking place April 18 – June 15, was part of a regularly scheduled maintenance, which occurs every five years.

“Five years is just a historical mark,” said Jay Dehart , 733rd Logistics Readiness Squadron harbormaster. “We’ve figured that within five years [Skiffe’s Creek] starts filling back in. Where the river turns faster, water goes around the corner on the inside, slower water on the outside, causing huge amounts of sediment in the channel.”

The cyclical nature of the water’s current necessitates the dredging as filled-in waterways can impede ship movement in and around the piers. Those ships using the piers, because of buildup of sediment, were getting hung up there.

At the piers are cargo ramps, which allow for a ship’s bow ramp to lower for the embarkation or discharge of cargo. Some of these ramps were no longer accessible due to the sand and silt accumulation as the regular five-year mark approached.

“The controlling depth of the channel going in is 20-feet deep. Most of those boats are drafted in about 14 [feet],” said Dehart. “And so as [the boats] were coming in the channel, they were actually running aground at low tide. So it was time to come in and clean it all back out; get [the depth] back out to 20 [feet].”

According to the officials, the dredging project had removed 491,426 cubic yards of material from the bottom of Skiffe’s Creek.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Infrastructure

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Boskalis: Geopolitical tensions in the Middle East adversely impact activity levels
  2. 2Anaklia dredging project accelerates with two Jan De Nul TSHDs in the area
  3. 3VIDEO: Damen TSHD Kapuka gears up for sea trials
  4. 4Spotlight on Tuvalu Coastal Adaptation Project in Funafuti

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free